Update: Bridge replacement over I-24 in Dade County completed

The bridge is the overpass for the I-24 at Exit 169 (SR 299) interchange, located approximately 0.6 miles south of the Georgia/Tennessee state line. (Image: G-DOT)

UPDATE: 6:30am Tuesday:

The bridge of GA-299 over I-24 reopened at 6 a.m. Tuesday.

UPDATE: 4:30 pm Monday:

The GDOT says crews are still working to finish the Accelerated Replacement project.

GDOT says schedule updates will be provided when available, but for now the bridge remains closed.



UPDATE: Monday noon:

Wright Brothers Construction now says there were complications with the demolition of the old bridge, and with the machine that will move the new bridge into place.

They tell us they do not know if the project will be finished today.

Depend on us to keep you posted.

UPDATE: On Monday morning, crews were hoping to have the work done by midday. Depend on us to keep you posted.



UPDATE: As of Sunday afternoon, GDOT says the bridge is halfway complete.

-----------------------------------------------


Georgia DOT contractors will close and replace the SR 299 at I-24 bridge in Dade County starting Friday, May 12th at 9:00 p.m. through Monday, May 15th at 5:00 a.m.

Check out a live feed of the construction here.


Georgia DOT says for the first time it is employing an innovative building method called Accelerated Bridge Construction (ABC) to minimize the project’s impact on the environment and traveling public. This technique will contain the existing bridge removal and new bridge installation within a single weekend (56 hours).

The bridge is the overpass for the I-24 at Exit 169 (SR 299) interchange, located approximately 0.6 miles south of the Georgia/Tennessee state line. Clearly marked detours will reroute travelers around the SR 299 bridge and associated loop ramps. (see map above)

The SR 299 bridge replacement is the debut of the ABC method in Georgia. “Taking care of our bridges is a high priority within the Department,” says Andrew Hoenig, Georgia DOT Senior Project Manager. “Being able to replace a bridge in an accelerated time frame allows us to apply industry innovation and complete the construction much sooner than a standard bridge reconstruction.”

For more information about this project and to view the live feed, go here.

LANE SHIFT SCHEDULE

(Note: All times are approximate based on the current schedule. Exact hours are subject to change.)

  • On Thursday, May 11 starting at 9 p.m., I-24 eastbound traffic will begin utilizing the median crossover within the project limits. Once crossover is complete, all four I-24 lanes will travel under the westbound bridge span. (Work on the I-24 eastbound bridge span will start Friday, May 12 at 9 p.m.)
  • On Saturday, May 13 between 10 – 11 a.m., eastbound traffic will be switched from the I-24 median crossover back to the regular I-24 eastbound lane configuration. I-24 westbound traffic will then be switched into the I-24 median crossover, and all four I-24 lanes will travel under the eastbound bridge span.
  • On Sunday, May 14 between 2 – 3 a.m., I-24 westbound traffic will be switched back to the regular I-24 westbound lane configuration.
  • On Monday, May 15 between 4 – 5 a.m., the SR 299 bridge will be opened to traffic.